BMC to start resurfacing of roads soonIllustrative image – not actual.
The Brihanmumbai Municipal Corporation (BMC) will commence reconstruction and resurfacing of roads in a coming few days. The process will begin after BMC gets permissions from the Traffic Department.

It had earlier planned to begin road reconstruction from 1 October 2018 which did not happen as there was a delay in getting permissions from the Traffic Department.

The work on the roads will be carried out in phases. In all, there are 1,343 road works, of which only 719 roads are remaining, since these were put on hold during monsoon. The total length of roads on which work is pending is around 305 km. It is yet to be decided as to how much time and how many phases will be required to complete the work.

The tendering process for 624 works for 202.31 km roads is already completed. However, work of the remaining 719 roads will begin in a short while. Of 624 km road works, reconstruction and resurfacing for 46 km road will be done on 199 roads in the city; 47 km on 155 roads in eastern suburbs and 108 km on 270 roads in western suburbs. The work will be done on priority basis.

← All latest storiesBack to top →