Illustrative image – not actual.The Brihanmumbai Municipal Corporation (BMC) will reclaim two more acre land near Girgaum Chowpatty and Priyadarshini Park, as part of work on the two underground tunnels for the coastal road.
The 3.45 km underground twin tunnels which are part of the Rs 12,721 crore Phase-I of the project, will start from Princess Street flyover to Priyadarshini Park, running under Girgaum Chowpatty and Malabar Hill. The work at these areas, chosen to avoid slowing down traffic in South Mumbai, is likely to begin from 1 November 2018, according to a civic official.
The tunnel boring machine (TBM) will begin the excavation work near Priyadarshini Park and it will be retrieved at a site around Girgaum Chowpatty, near the Thackers Club. The work is expected to be completed in 48 months.
The three companies will also have to submit a primary design to the civic body within three months, starting from 1 October 2018. In the start of October 2018 the BMC gave its final approval to the construction of Phase-I of the coastal road -- 9.98 km road between Princess Street flyover and Bandra-Worli Sea Link (BWSL).
The construction of the road, which is divided into three packages, will begin simultaneously. BMC will reclaim 90 ha for the project. Of this 70 ha will be available for landscaping and for other facilities like a police chowky, public toilets, pedestrian crossing and bus stops. The coastal road will be constructed on 23 percent of the reclaimed land.