BMC to complete boring of 2nd tunnel by January 2023 for Coastal RoadIllustrative image – not actual.

The BMC plans to complete boring works of the second tunnel by next month to comply with the November 2023 deadline for completion of the Mumbai Coastal Road Project.

The 10.6-km coastal road stretching from Princess Street in Marine Drive to the Worli end of Bandra-Worli Sea Link will comprise twin tunnels, each 2.07 km long, from Priyadarshini Park to Girgaum Chowpatty for improved connectivity.

The boring work for the second tunnel will be completed by January 2023. Post completion, internal tunnelling works such as construction of the utility box, surface areas, cross passageways and firefighting systems will be carried out.

The current project status shows that 67 percent of the overall project has been completed with reclamation of 111 hectares.

The 12.2m-wide Tunnel Boring Machine (TBM) being used for the boring work is the biggest and also the first-of-its-kind to be used for under-sea tunnel being executed in the country.