BMC sets  new completion target for first cable-stayed railway bridgeIllustrative image – not actual.

The Brihanmumbai Municipal Corporation (BMC) has set a new deadline to complete Mumbai’s first cable-stayed bridge over railway tracks near Mahalaxmi station, connecting Saat Rasta with Mahalaxmi Maidan.

Additional Municipal Commissioner (Projects) Abhijit Bangar inspected the ongoing construction on Keshavrao Khadye Marg and directed officials to accelerate the remaining work. The project is being executed under the city’s Development Plan works. A 78.5-mtrs.-high pylon supporting the cable-stayed structure has already been constructed. Work on the eastern span, located within railway premises, will begin after the BMC receives the required railway block. The BMC is constructing a concrete service road to facilitate traffic movement during construction, while utility-laying work is also underway.

The civic body has pushed its completion target from 31 October to December 2026.