Illustrative image – not actual.The Brihanmumbai Municipal Corporation (BMC) is all set to scrap the Rs 4,500 crore Deonar dumping ground scientific closure and waste treatment project.
The contract was awarded to Tatva Global Environment, led by United Phosphorus (UPL) six years ago. The final call on this issue will be taken by newly appointed civic chief, Ajoy Mehta.
The BMC had agreed to pay the company nearly 1,400 times the amount initially proposed by its own consultant. From Rs 40 per tonne as a tipping fee for processing the waste dumped at the 134 ha ground to finally agreeing to pay Rs 550 per tonne, the civic body ended up paying 1,375 times more for the same work. The total cost reaches Rs 4,408 crore. Despite the escalations, the company has not begun processing waste at the ground.
As per the company, the BMC failed to hand over the land on a leasehold basis as mentioned in the contract.
The civic body will scrap the contract and float fresh tenders.