BMC aims to open Gokhale Bridge in Mumbai by MayIllustrative image – not actual.

Brihanmumbai Municipal Corporation (BMC) has started to expedite the completion of the second arm of Gokhale Bridge in Andheri, aiming to open by May 2025.

MLA Ameet Satam, after inspecting the site, confirmed that work is progressing rapidly. On the east side, most structural elements are in place, with final pier caps, girders, and ramp work pending. The west side has also seen significant progress, with only three girders left to be installed.

Initially closed in November 2022 due to severe structural damage from corrosion, the bridge’s first arm was reopened in February 2024. However, a six-ft. gap with the C D Barfiwala flyover rendered the latter unusable. BMC, with IIT-B and VJTI experts, worked on fixing the gap, completing the alignment on 04 July, 2024.