Blue Star secures order from Bangalore Metro Rail CorpIllustrative image – not actual.

Blue Star has bagged an order from the Bangalore Metro Rail Corporation (BMRCL) in Karnataka.

The order worth Rs 84 crore is for the environmental control system and building management system for the seven underground stations of the Phase I of Bangalore metro rail project. The scope of work includes design, supply, installation, testing and commissioning of chillers, pumps, air handling units, fan coil units, cooling towers, ventilation fans, motor control centre panels and building management system along with the associated work of piping, ducting, grilles and insulation.

The Phase I of the metro rail project consists of double line electrified North-South and East–West corridor, covering a total length of 42.30 km. The East-West corridor will be 18.10 km long and the North- South corridor will be 24.20 km. Out of the 42.30 km., 8.82 km will be underground and the rest will be elevated.