Illustrative image – not actual.The Aditya Birla group and PowerGen, the promoters of 578 MW Bina Power project have tied up funds from financial institutions for the project, pushing the project towards financial closure.
The total cost of the project is
estimated at Rs.2,906 crore, with an equity component of Rs.872 crore and a
debt component of Rs.2,034 crore. PowerGen holds a 40 per cent equity stake in the
project, while the Birla group holds the remaining 51 per cent stake.
The financial institutions have
however, laid a condition that the Madhya Pradesh Electricity Board should
provide an escrow cover for 693.6 MW, i.e an escrow cover of 1.2 MW for every
mega watt of installed capacity.
This move has also improved the
prospects for PowerGen, which plans to sell its stake in the project, as after financial
closure, PowerGen’s stake will fetch a better price. PowerGen plans to sell its
assets in India, Indonesia, Australia and New Zealand to collect funds to buy
out the $3.2 billlion LG&E Energy Corporate.
The other milestones achieved by the
project are PPA signed in 1996, CEA clearance in 1997 and fuel supply agreement
with Coalfields and the Railways.