Bikaner-Phalodi road project soon in RajasthanIllustrative image – not actual.
As confirmed with Projects Today, Ircon International is all set to make its Bikaner-Phalodi road project in Rajasthan operational by June 2019. In 2014, the National Highways Authority of India (NHAI) awarded the highway building contract to the concessionaire, Ircon International.

The scope of the contract envisages widening and strengthening of the existing Bikaner-Phalodi section to four-lane from 4.200 km to 55.250 km and two-lane with paved shoulder from 55.250 km to 163.500 km of NH-15.

The project worth Rs 822.9 crore was approved by the Public Private Partnership Approval Committee (PPPAC) and the Cabinet Committee on Economic Affairs (CCEA) to be implemented on build operate transfer (BOT) on toll basis.

The foundation stone for the project was laid in December 2014. In April 2015, the project achieved financial closure. Following this, work on the road project commenced with an official completion deadline of April 2018. However, delays forced the company to extend the completion date to November 2019.

As of date, Ircon International has managed to complete 90 percent of the road project. The project will be ready five months ahead of the official completion date. Stup Consultant was appointed as consultant.