Illustrative image – not actual.The Bihar Urban Infrastructure Devp Corpn has invited bids for works on two sewage treatment plants in Bihar.
The scope of work involves design, build and finance of two sewage treatment plants of 100 MLD and 50 MLD including SCADA and online monitoring system, effluent channel, interception and diversion works within 21 months and operate and maintain the complete works for 15 years and their transfer at the end of concession, survey, review the designs, redesign and build sewerage network of 303 km length in Digha.
The sewage network of 150 km will be built in Kankarbagh, including construction of four pumping stations, SCADA and all appurtenant structure and allied works within 31 months and operate and maintain the complete works till the end of concession and their transfer at the end of concession in Digha and Kankarbagh zones of Patna district in Bihar.