Bids invited for the construction of substations and transmission line in UPIllustrative image – not actual.

Uttar Pradesh Power Transmission Corporation (UPPTCL) has invited bids for the construction of substations and transmission line under procurement of works across districts of the state.

Under Package-19, the work comprises the engineering, supply, erection and commissioning of 220/132/33kV sub-station, (1xl60+1x40 MVA) Birdha (Lalitpur), Birdha (Lalitpur)-Lalitpur 220 kV transmission lines on 30 km D/C line including supply of equipment, erection, testing, and successful commissioning and related civil works. 

The EPC turnkey contract is estimated at Rs 327.29 crore, and is to be completed in a timeframe of 18 months.

The last date to submit the bid is 13 September, 2023.