Illustrative image – not actual.The government of Uttar Pradesh has invited bids for
prospective joint venture partners for construction and operation of the
proposed six-lane 160 km expressway connecting New Delhi and Agra.
The joint venture partner would be responsible for the preparation
of the detailed project report (DPR), arrangement of finances, and for the
construction and operation of the expressway. The JV partner would hold 76 per
cent equity in the joint venture with Taj Expressway Authority (a
special purpose vehicle owned by the Government of Uttar Pradesh) holding the
remaining 24 per cent.
The estimated cost of the project is $350 million (approx
Rs.1,600 crore). The first phase of the expressway between Noida Toll Bridge
and Greater Noida (around 25 km) is already under construction.
The expressway would reduce the travelling time between New
Delhi and Agra to around 100 minutes. The main expressway would pass through
virgin land along river Yamuna. A band
of around 0.5 km of land along the expressway would be offered for commercial
development. The project is expected to be completed within three years.
The project, to be undertaken on a BOT basis, would have a
concession period of 40 years.
The last date for submission of tenders is 31 July 2001.
For more details, visit http://www.greaternoida.com
Follow-up:
In
a subsequent clarification issued by the Taj Expressway Authority on 28 May
2001, the joint venture partner would hold 75 equity stake in the joint
venture while the Taj Expressway Authority would hold the remaining 25 per
cent.