Bids invited for Coal Handling Plant at Amrapali OCP, JharkhandIllustrative image – not actual.

The Central Coalfields has invited bids for the construction, and commissioning of a coal handling plant (CHP) with silo loading arrangement at Amrapali OCP, located at Chatra district in Jharkhand on a turnkey basis.

The construction, installation, testing, trial run and commissioning of CHP (25.0 MTY), consists of all civil, structural, electrical and mechanical works and all other accessories and facilities required to make it complete.

The estimated cost is Rs 527.36 crore, and the construction of plant including trial run, PGT and commissioning is to be carried out in 24 months. The operation and maintenance of the plant will extend for 60 months.

The work is required to commence within 30 days from the issue of letter of acceptance or seven days after handing over the site for the first activity as per PERT network chart, whichever is later.

The last date for bid submission is 16 August, 2023.