Illustrative image – not actual.National Thermal Power Corporation (NTPC) would float bids for the EPC contract of its Gandhar plant in Gujarat soon. The 1,300 MW plant is coming up with an investment of Rs.5,200 crore.
The plant is part of the X Plan (2002-07) of the company. The targeted capacity of the plan is 9,370 MW. NTPC recently completed bidding of the Badh (Bihar) and Kawas (Gujarat) plants, which have respective capacities of 1,980 MW and 1,300 MW.
Out of planned 9,370 MW capacity, 2,500 MW has already been commissioned, 1,500 MW is in its advanced stages of implementation and 4,200 MW is expected to be commissioned in the next four months.
Included as part of this 4200 MW capacity are plants in Kelgam (1500 MW, Bihar), Vindhyachal (1,000 MW, Uttar Pradesh) and Sipat (980MW, Chhattisgarh).
NTPC will start implementation of the plants at Talchar in Orrisa and Rechind in UP with a total capacity of 500 MW.
NTPC's current installed capacity is 23,400 MW and it aims at adding 11,400 MW in the XI Plan period (2007-12). By 2012, NTPC has targeted capacity of 40,000 MW and 56,000 MW, by 2017.
Meanwhile, the company’s 800 MW Koldam hydropower project in Himachal Pradesh will be completed by November 2008.