Illustrative image – not actual.Uttar Pradesh government has yet again extended the bidding date for a power plant to be set up in Allahabad, Uttar Pradesh due to higher tariff quotes. Now, the new date for submitting the bids has been extended to 5 January 2009.
The government wants to set up a 1,980 MW thermal power plant at Bara in Allahabad based on super-critical technology.
Uttar Pradesh government is of the view that in the prevailing economic situation, the bidders will quote a higher price for supplying electricity; therefore the corporation is buying time.
Earlier, the bid date was extended from 30 November to 15 December 2008. Nine companies - NTPC, Indiabulls, JP Power Ventures, Lanco Kondapalli, GVK, L&T, Adani Power, Reliance and Isolux - were in the fray to bid for the power project.
Also See:
Uttar Pradesh extends financial bid for power plants(06-Dec-08)