Bidadi Power Project may not be viableIllustrative image – not actual.

The 200 MW naphtha-based Bidadi Power project coming up in Karnataka does not seem to be viable given the current upward trend in international oil prices and the weakening of the rupee.

 

On the basis of the current oil prices and exchange rates, the effective power tariff works out to Rs.5 per unit as against an average of Rs.1.90 per unit being paid currently by the Karnataka Power Corporation.

 

The Rs.770 crore Bidadi project is being jointly set up by Unocal of USA and Karnataka Power Corporation.

 

The project was to go into financial closure in July 2000. However, with the viability of the project now in serious uncertainty, the project may not achieve this milestone in the near future.