Illustrative image – not actual.On 15 February 2001, the Maharashtra Government’s high-powered committee on industry cleared Bhushan Steel & Strips' cold rolled (CR) steel project in Maharashtra.
The Rs.750 crore CR galvanising sheet project would have a capacity of 3 lakh tonnes per annum. It would be set up at Rasayani near Raigad in Maharashtra. The project is expected to employ at least 1,200 people.
The source of funds for the project, however, remains
uncertain, since the company has not yet approached financial institutions for
funds. According to officials of IDBI and ICICI, project clearance could take
time. It may be recalled that financial institutions were earlier (in 2000) reluctant
to lend to the company’s proposed project.
The State Government also cleared the company’s plan
to set up a 29 MW power plant. Of the total capacity, the company plans to sell
5 MW to the Maharashtra State Electricity Board, while the remaining would be
used for captive purposes.