Illustrative image – not actual.Bhushan Steel is likely to sign an MoU with the Orissa Government which will pave the way for the company mining 3.5 million tonne of iron ore a year for its new steel projects.
The company is setting up a 2.5 million tpa steel plant in Meramandali in the state which is slated to be commissioned in the third quarter of this year. The mining agreement with the state Government will be a separate arrangement which the state government will be doing for the company, and as such, will not fall under the volume restriction on merchant mining in the state.
The Phase I (0.3million tpa) of this expansion was completed in 2009 while phase II (two million tpa) was completed in 2009-10. Work on the Phase III is in full swing and the management expects it to commission in the current financial year. On completion, the company will have a total capacity of about 5.2 million tonne.