Bhubaneswar Municipal Corporation is likely to miss its deadline for a new hospital and for the upgradation of five existing dispensaries in Odisha.
On 7April 2017, the Bhubaneswar Municipal Corporation entered into an agreement with Krishna Institute of Medical Sciences (KIMS) to set up a 400-bed multi-disciplinary hospital at Gadakana and to upgrade five existing dispensaries at Kapilaprasad, Brahmeswarpatna, Gadakana, Rasulgarh and Bharatpur into primary and secondary healthcare centres.
Neither of these projects has seen any progress.
As per the agreement, KIMS was supposed to complete the project by April 2019. However, the company has failed to avail of a loan for the Rs 255crore project.
The company is facing funds-related problems after the banks revised the norms post demonetisation.
The project will be executed in public-private partnership (PPP) mode. The private partner will have to bear the entire cost while the civic body will only provide the land.
The hospital project was originally planned and the foundation stone for the same was laid in August 2015.
The cost of the project has now escalated from Rs 200 crore to Rs 255 crore.