Bhogapuram International Airport operations expected by July-AugustIllustrative image – not actual.

Operations at Bhogapuram International Airport in Andhra Pradesh are expected to begin between July and August 2026, with project work nearing completion, Roads and Buildings Minister B C Janardhan Reddy announced.

After inspecting the site with MSME Minister Kondapalli Srinivas, he said inauguration dates under consideration include July 5, July 8, August 17, or August 19, depending on Prime Minister Narendra Modi’s availability, while Chief Minister N Chandrababu Naidu will finalise the schedule. The airport project, which started in 2014, experienced slow progress initially but gained momentum after the Chief Minister reviewed pending issues and facilitated approvals. The Union Civil Aviation Minister, Kinjarapu Ram Mohan Naidu, also played a key role in advancing the project. Officials report that over 98 percent of the work is complete. Earthworks, runway, and taxiway construction have been finished, while the passenger terminal building is nearly complete at 98.76 percent.

The Air Traffic Control tower stands at 95.75 percent completion, ancillary buildings at 93.54 percent, and the main access road at roughly 90 percent. With construction almost done, the airport is on track to become a key aviation hub in the region, enhancing connectivity and supporting economic growth.

← All latest storiesBack to top →