Bhogapuram airport completion likely ahead of scheduleIllustrative image – not actual.

GMR Airports targets to operationalise the Bhogapuram airport in the second quarter of the current fiscal year, significantly ahead of its earlier target of December 2026.

GMR Airports is likely to incur capital expenditure in FY2026–FY2027 largely on the Bhogapuram International Airport project, while its other airports will incur only operational capex.

It expects to spend around Rs 700–800 crore on the Bhogapuram airport during FY2027 to complete the project. As of March 2026, the airport had achieved 98.7% physical progress.

The Bhogapuram project remains the company's key growth investment, with construction nearing completion and commissioning activities progressing towards commercial operations.