Illustrative image – not actual.BHEL commissioned it 430 mw
combined cycle power plant at Faridabad in Haryana. The power plant was set up
by NTPC. The gas turbines and steam turbine generator for the project was
manufactured at BHEL’s Haridwar plant, while the HRSGs were manufactured at its
Trich plant. The controls, instrumentation and electricals were manufactured at
the electronics division of the Bangalore and Bhopal units.
The Rs.697 crore project was
funded by Japan Bank of International Corporation. BHEL had bagged this project
in Jaunary 1998.