BHEL's 430 MW power plant at FaridabadIllustrative image – not actual.

BHEL commissioned it 430 mw combined cycle power plant at Faridabad in Haryana. The power plant was set up by NTPC. The gas turbines and steam turbine generator for the project was manufactured at BHEL’s Haridwar plant, while the HRSGs were manufactured at its Trich plant. The controls, instrumentation and electricals were manufactured at the electronics division of the Bangalore and Bhopal units.

 

The Rs.697 crore project was funded by Japan Bank of International Corporation. BHEL had bagged this project in Jaunary 1998.