BHEL wins CPCL contractIllustrative image – not actual.

State-owned power plant equipment manufacturer Bharat Heavy Electricals announced on 7 February 2002, that it has won a Rs.174 crore order to set up a 40 MW power plant for Chennai Petroleum Corporation Ltd.

 

The gas-based co-generation power plant would be part of CPCL's refinery expansion at Chennai and is scheduled to be completed in 17 months.

 

The order includes supply and commissioning of two 20 MW gas turbines and two 52 tonnes-per-hour heat recovery steam generators and associated equipment.

← All latest storiesBack to top →