BHEL synchronises 490 MW Unit at Dadri plantIllustrative image – not actual.

BHEL has synchcronised the Unit I 490 MW of the National Capital Thermal Power Project Stage-II, at Dadri in Uttar Pradesh.

The unit is equipped with a high temperature reheat steam turbine which has been designed for operating at a higher reheat steam temperature of 565 degree celsius aimed at reducing the consumption of coal. The unit also comprises an advanced control, instrumentation and monitoring system.

BHEL's scope of work in the contract envisaged manufacture, supply, erection, testing and commissioning of the main plant package for two units of 490 MW each. The second unit is in an advance stage of erection and is expected to go on stream shortly.

Related Links:
Project profile

 

← All latest storiesBack to top →