BHEL installs boiler drum at RTPS Unit 7Illustrative image – not actual.

Bharat Heavy Electricals Ltd (BHEL) has installed the 125 tonne boiler drum at 210 MW Raichur Thermal Power Station (RTPS) Unit 7 in Karnataka on 31 October 2001. A boiler drum lift is the first major milestone in the construction of a thermal plant.

 

BHEL has positioned the boiler drum for the Unit 7 at an elevation of 52 metres in 12 months, ahead of schedule.

 

Unit 7 of the RTPS, promoted by Karnataka Power Corporation, is expected to be synchronised by December 2002 / January 2003, i.e. in just 26 months from zero date. This unit is estimated to cost Rs.613 crore.