Illustrative image – not actual.Bharat Heavy Electricals Ltd (BHEL) in Hardwar will invest Rs.1,600 crore in the next five years to enhance its capacity and deliver 600-800 Mw generators and steam turbines. Currently, BHEL's Heavy Electrical Equipment Plant (HEEP) at Ranipur in Hardwar manufactures 200-500 Mw range generators and steam turbines for thermal plants.
BHEL-Hardwar has an expansion plan to increase its capacity to10,000 Mw by 2009, for which the company is to produce16 high Mega-Watt generators and about 60 steam turbines in 2007. BHEL's enhancement endeavours come at a time when the government has planned a capacity addition of 70,000 Mw in the Eleventh Plan. The government's plan for ultra mega power projects (UMPP) also raised the demand for power equipments. BHEL has a technological tie-up with Siemens for manufacturing these high Megawatt sets.
Also see
BHEL to add over 21,000 MW in X Plan (15-Feb-2006)