Illustrative image – not actual.BHEL on 17 February 2011 conducted test run of its first indigenously manufactured turbine.
The first advanced class 9FA+e (250 MW) gas turbine has been developed in collaboration with GE of the US. It has been manufactured at BHEL Ramchandrapuram, Hyderabad. The company is planning to deliver two more units by March 2011.
The value of the test facility is Rs 400 crore. This new test facility has many features which were hitherto never been established before. The unique features of this advanced Gas Turbine are use of HSD (High Speed Diesel) as fuel. The entire control system was designed and configured by BHEL indigenously.
Also See:
Pragati-II power plant gets approval (15-Feb-11)