Bharat Heavy Electricals Ltd (BHEL) announced the commissioning of its 200 MW national high voltage direct current (HVDC) Project, Stage II.

 

The project, which was executed by BHEL on a turnkey basis, has linked the 196 km DC transmission line between Barsoor in Chhattisgarh and lower Sileru in Andhra Pradesh.

 

The 200 MW, 200 KV stage II of the project is an upgradation of the existing 100 MW, 100 KV stage I project which was completed in 1989.

 

The project was jointly funded by the Department of Heavy Industries, Ministry of Power, Ministry of Information & Technology, BHEL, and the State Electricity Boards of Andhra Pradesh and Madhya Pradesh.