Bharat
Heavy Electricals Ltd (BHEL) announced the commissioning of its 200 MW national
high voltage direct current (HVDC) Project, Stage II.
The
project, which was executed by BHEL on a turnkey basis, has linked the 196 km
DC transmission line between Barsoor in Chhattisgarh and lower Sileru in Andhra
Pradesh.
The
200 MW, 200 KV stage II of the project is an upgradation of the existing 100
MW, 100 KV stage I project which was completed in 1989.
The
project was jointly funded by the Department of Heavy Industries, Ministry of
Power, Ministry of Information & Technology, BHEL, and the State
Electricity Boards of Andhra Pradesh and Madhya Pradesh.