After successfully running for over 30 years, this unit, originally supplied and commissioned by BHEL, was undertaken for renovation & modernization (R&M).
Post R&M, the working life of the machine extended by 15-20 years, the capacity was uprated to 120 MW from its original capacity of I l0 MW.
This is the eighth unit successfully renovated, modernised and uprated by BHEL from its original rating of 110 MW to 120 MW.