BHEL commissions first unit of 82.5 MW GVK projectIllustrative image – not actual.
Bharat Heavy Electricals (BHEL) has successfully commissioned the first unit of 82.5 MW at the upcoming Srinagar Hydro Electric Project (HEP) in Uttarakhand. The greenfield hydro electric project consisting of four units of 82.5 MW each is being set up by Alaknanda Hydro Power Corporation (GVK Group).

 

The scope of work includes design, manufacture, supply, installation and commissioning of four units of 82.5 MW francis turbines, generators, static excitation, generator, transformer, unit transformer, station transformer, main inlet valve, digital governors, control & monitoring system (SCADA), busduct, associated station auxiliaries, 400 kV switchyard and electrical & mechanical balance of plant (BOP).

 

This project is designed to utilise the waters of the river Alaknanda by way of a diversion dam. The power generation from this plant is likely to result in reduction of greenhouse gas emissions.

 

Presently, BHEL is executing hydro electric projects of around 4,000 MW, which are under various stages of implementation. Other projects under execution in Uttarakhand include Lata Tapovan HEP (3x57 MW), Tapovan Vishnugarh HEP (4x130 MW), Vyasi HEP (2x60 MW) and Vishnugarh Pipalkoti HEP (4x111 MW).

 

More Project Info:
Srinagar Hydel Power Project

← All latest storiesBack to top →