Illustrative image – not actual.
With this, eight units aggregating 2,840 MW, supplied and executed by BHEL, are now in operation at Chandrapur STPP. Also, work on the second 500 MW unit of Stage-III of the project is in progress and is expected to be commissioned in the financial year 2015-16.
As per the contract, the scope of work is design, engineering, manufacture, supply, erection and commissioning of steam turbines, generators and boilers along with associated auxiliaries and electricals, besides state-of-the-art controls and instrumentation (C&I) and electrostatic precipitators (ESPs).
BHEL has been a partner in the power development programme of the state of Maharashtra and has contributed more than 15,000 MW of generating capacity to the state. This is the highest in any single state.
More Project Info:
Chandrapur Thermal Power Station - Expansion