The second unit of 195 MW is expected to be commissioned in FY 2015-16. The scope of work for BHEL in the Muzaffarpur project is design, engineering, manufacture, supply, erection and commissioning of steam turbines, generators and boilers, along with associated auxiliaries and electricals, besides state-of-the- art controls & instrumentation (C&I) and electrostatic precipitators (ESPs).
Earlier, BHEL has commissioned a 660 MW supercritical thermal unit at Barh in Bihar, in the first week of March, 2015.
More Project Info:
Muzaffarpur Coal Based Power Project - (Stage II)