Illustrative image – not actual.Bharat Heavy Electricals (BHEL) has bagged a Rs.62.7 crore contract from National Thermal Power Corporation for the engineering, supply erection, testing and commissioning of a coal handling plant for the Rihand super thermal power project, Stage II (2 x 500 MW).
The contract would be executed on a turnkey basis by BHEL’s
Industrial Systems Group (ISG), Bangalore.
As per the contract, ISG would supply all the technological
equipment including crushers, screens, paddle feeders, stacker/reclaimer,
travelling trippers, conveyor system, associated electricals and automation
systems and complete civil and structurals work related to the coal handling
facility.
The power project is expected to be completed in 35
months.