Illustrative image – not actual.Bharat Heavy Eletricals (BHEL) has bagged an order worth Rs.21 crore for supply of power generating equipment to Jindal Stainless (JSL) for its upcoming project in Orissa.
The order to be executed is for the main plant and equipment for the captive power plant to be installed as part of JSL's Duburi Stainless Steel plant. This is the second order that has been placed with BHEL by JSL.
The scope of work includes manufacture, supply, erection and commissioning of one 13 MW steam turbine generator (STG) set with associated auxiliaries and two waste heat recovery boilers (WHRB) of 28.5 tonnes per hour capacity each.
The STG set will be manufactured and supplied from BHEL's Hyderabad plant,while the WHRBs are to be supplied by its Tiruchy unit. The project work is expected to be completed by 16 months.