Illustrative image – not actual.Bharat Heavy Electricals has reportedly been awarded the engineering, procurement and construction contract worth at least Rs.2,467 crore for the Nagarjuna Power Corporation's 1,015 MW Mangalore power project.
The only other contender for the contract was the Chinese consortium comprising China Non-metal Enterprises group and the China Machine Building International Group.
This is the first time that Bhel has secured such a large value contract from an independent power producer through the competitive bidding route. The contract is to be executed in phases. The first phase of the project would have to be completed within 38 months after the financial closure and second phase within 42 months. Bhel winning the contract would reduce the foreign currency component in the Rs.4,500 crore power project.
The Simplex group would implement the civil construction for the project which would worth about Rs.980 crore.
Status of the Nagarjuna Power Project:
The project financing were in place. The components included the three-tier
financial security package -- a letter of credit, an escrow account and state
government guarantee.
The foreign equity component was also in the process of being tied up. However NPCL has not yet firmed the foreign partner for the project.
The promoters, which include Nagarjuna Fertilisers and its group companies would infuse 51 per cent stake in the total paid up capital estimated at Rs.1,350 crore. The promoter group would bring in Rs.690 crore as part of their equity. The foreign partners would be expected to bring in the remaining 49 per cent of the stake or about Rs.660 crore of the equity.
The company has already tied up with Australian suppliers for supply of fuel for the project. The project coal requirement is estimated at 1.5 million tpa of coal with a calorific value of 6,000 kilocalories per kilogramme.