Illustrative image – not actual.Bharat Heavy Electricals (BHEL) has bagged the contract for setting up the 250 MW fifth unit of the Suratgarh thermal power station in Rajasthan.
BHEL would undertake the design,
manufacture, supply, erection, testing and commissioning of the main plant equipment
for the 250 MW set with associated auxiliaries.
BHEL had also bagged the orders for
the power plant’s first four units of 250 MW each.
It may be recalled that the foundation
stone of the fifth unit (250 MW) of Suratgarh Super Thermal Power Station
(SSTPS) was laid on 12 February 2001, by Mr Suresh Prabhu, Union Minister for
Power.
Rajasthan
Rajya Vidyut Prasaran Nigam, a state government undertaking, is implementing
this project.
The
SSTPS project is the first super thermal power station in Rajasthan, envisaging
the setting up of five power stations of capacity 250 MW each. The total
investment is to the tune of Rs.5,000 crore.
The
first and second unit of the SSTPS have started commercial generation in
February 1999 and July 2000, respectively.
The
third and fourth units are expected to begin commercial generation in March
2002 and September 2002, respectively.
The
fifth unit, for which BHEL has bagged the contract, is slated for commercial generation in June 2003.