Illustrative image – not actual.Hindustan Petroleum Corporation (HPCL) has plans to scale down the capacity of its refinery at Bhatinda from 9 million tonnes per annum (mmtpa) to 6 mmtpa. The project is expected to be completed by December 2006.
The decision came in wake of the slowdown in the demand for petroleum products.
The expenditure for the project is Rs.276.25 crore.
The refinery would have product tanks for motor spirit, superior kerosene and high-speed diesel, crude pipeline and associated facilities. It will also have naphtha hydrotreater, continuous catalytic reformer, naphtha isonerisation unit, naphtha cracking unit, hydrogen production unit, and liquefied natural gas (LPG) storage.
The refinery would have a crude distillation unit, vacuum distillation unit, once-thru hydrocracker, deep catalytic cracker, diesel hydrotreater, vacuum residue desulphurisation sweetening units, bitumen blowing unit, FCC naphtha hydrotreater, sulphur recovery unit and associated facilities.