Bharuch-Surat expressway reaches financial closureIllustrative image – not actual.

IDAA Infrastructure Pvt Ltd, on 6 December 2006, attained financial closure for the 65-km Bharuch-Surat section of NH-8 in Gujarat -- the first project to be awarded under NHDP-V.

NHAI had awarded this BOT project in July 2006 and the winning consortium was expected to attain financial closure within six months. IDAA Infrastructure had quoted a negative grant of Rs.504 crore (payable to NHAI) for developing this Rs.492 crore project on BOT basis for a concession period of 15 years, including construction time.

The broad details of the project are:

Section: Bharuch-Surat Section (NH-8)

State: Gujarat

Project: NHDP-V

Length: 65 km (km 198 to km 263) on NH-8

Execution: BOT model

Concessionaire: IDAA Infrastructure Pvt Ltd (four-member consortium)

Cost: Rs.492

Completion: 30 months

Concession period: 15 years, including construction time

Grant: Rs.504 crore (Negative, payable upfront TO NHAI)

IIPL also presented this negative grant to NHAI. The amount was received by Prime Minister, Dr Manmohan Singh, on behalf of NHAI.

The members of IIPL are IRB Infrastructure Developers Ltd (formerly Ideal Road Builders Ltd), Aryan Toll Pvt Ltd, ATR Infrastructure and DVJ Leasing & Finance.

Incidentally, the 83.3 km Vadodara-Bharuch section that was awarded to L&T Vadodara-Bharuch Tollways Pvt Ltd is expected to attain financial closure in January 2007. NHAI is expected to receive its negative grant of Rs.471 crore associated with this project shortly thereafter.

Note: Both the projects together represent the 148-km Vadodara-Surat section of NH-8 in Gujarat. This four-lane section will be converted into a six-lane expressway at a total cost of Rs.1,152 crore.

What is NHDP-V?

Under Phase V of NHDP, about 6,500 km of National Highways including 5,700 km on the Golden Quadrilateral would be widened from 4 to 6-lanes at a cost of Rs.41,210 crore. This would include development of corridors/sections with high density of traffic which are otherwise important for tourism or economic reasons. Although the project was formally approved by the CCEA in October 2006, NHAI signed the first two concession agreements (Bharuch-Surat and Vadodara-Bharuch sections) in July 2006 itself. This was done through specific government approval. During 2006-07, a total of 1,500 km are likely to be awarded under NHDP-V. This phase of NHDP is scheduled for completion by December 2012.