The timeline for Phase-II of BharatNet project, earlier slated to be completed by August 2021, will now be extended as its pace was affected by the lockdown due to COVID-19.
As on 1 September 2020, close to 23,133 Gram Panchayats (including block headquarters) have been made service ready, and 1.47 lakh km of optical fibre cable has been laid under BharatNet Phase-II.
As many as 65,000 Gram Panchayats in eight states are under implementation under the state-led model.
The delay in the implementation by the states is also adversely affecting completion of the project. For other states, not being implemented under the state-led model, the implementation strategy is under review.
It is planned to cover nearly six lakh villages in the country in 1,000 days from 15 August 2020.
The total cost of BharatNet, approved by the Union Cabinet in July 2017, stands at Rs 42,068 crore, and as on 1 September 2020, Rs 24,473 crore has been disbursed by Bharat Broadband Network (BBNL).