Illustrative image – not actual.Bharat Wire Ropes is setting up a wires unit with a capacity of 6,000 tpm at Plot No. 4, MIDC, Chalisgaon, in Jalgaon district of Maharashtra.
The project will be spread over 64 acre of land and implemented in two phases, Phase-I comprises 2,000 tpm capacity and Phase-II 4,000 tpm.
The project will be funded by term loans of Rs 330 crore from banks, fresh capital infusion of Rs 140 crore by the promoters and private equity players, and Rs 20 crore through internal accruals.
Work on Phase-I is underway with completion re-scheduled for July 2016.
Phase-II is expected to commence by October 2016.