After eight months of being stalled, work on the Bhama-Askhed water supply project has finally resumed after the district administration submitted a rehabilitation proposal to the state government for approval last week.
Work on the project had stopped in October last year following strong protests from the villagers of Karanj-Vihare.
The total cost of the Bhama Askhed project is around Rs 380 crore, of which approximately Rs 110 crore has already been spent. According to the project plan, Pune Municipal Corporation (PMC) envisions laying down a 42 km pipeline from Bhama-Askhed dam to Pune city, of which more than 30 percent has been finished. The earlier deadline for completion was July 2017.
The project was initiated in February 2014 to quench the thirst of the eastern part of the city, by supplying around 200 million litres per day (MLD) for future needs. The east of the city consists of Kharadi, Yerwada, Dhanori, Wadgaonsheri, Kalas and Vidyanagar, all of which face frequent water scarcity.