Bhagyanagar India has been awarded the letter of award (LoA) for a 53 MW solar power generator (SPG) under the Mukhyamantri Saur Krushi Vahini Yojana 2.0, a scheme designed for feeder-level solarisation under Component C of the PM-KUSUM Scheme.
The Maharashtra State Electricity Distribution Company (MSEDCL), a Government of Maharashtra undertaking, has allotted this project, which entails a total investment of Rs 245 crore. The solar project will be established in Maharashtra and is expected to be executed within 18 months from the issuance of the LoA.
The operation and maintenance (O&M) of the project will continue for 25 years from the commercial operation date (COD). The project has been awarded a tariff of Rs 3.09 per kWh, with financial assistance from the Government of India in the form of a subsidy amounting to Rs 1.05 crore per MW, under the central financial assistance (CFA) program.