Illustrative image – not actual.BGR Energy Systems has bagged balance of plant (BoP) contract for IB Valley expansion project of Odisha Power Generation Corporation (OPGC).
BGR Energy has received the balance of plant (BoP) contract worth Rs 1,573 crore - the expansion project wherein the state owned generator will add two 660 MW units to its existing power station.
The scope of the order includes supply, erection and commissioning of the BoP for OPGC's two units to be added at its Banharpalli plant near Jharsuguda. OPGC, a 51:49 JV between the Orissa Government and US-based AES Corporation, is currently operating two 210 MW units at the site.
OPGC has already achieved financial closure for the project. Physical construction of the expansion project will begin in two or three months. The company has already received statutory clearances required for the project. It is expecting to commission the proposed two units before March 2017.
The expansion project includes addition of two supercritical units, each of 660 MW, with an investment of Rs 11,547 crore, which also includes cost of other components like coal block development and dedicated rail corridor. The Ministry of Coal had allocated the Manoharpur and Manoharpur dip side coal blocks to OPGC for the project.