Illustrative image – not actual.Chennai based BGR Energy Systems, the EPC and BOP Turnkey engineering and contracting company for power projects, is arranging funds for its working capital requirements for execution of Tamil Nadu Electricity Board's 600 MW Mettur thermal power project.
The company estimated its fund based and non-fund based working capital facilities at Rs.2,105 crore and authorised SBI Capital Markets to arrange the financing facilities.
A consortium of banks led by State Bank of India evinced keen interest to finance these facilities. The structured funding facilities comprises participation from State Bank of India (Rs.525 crore), Indian Overseas Bank (Rs.580 crore), State Bank of Patiala (Rs.500 crore), Punjab National Bank (Rs.250 crore) & Vijaya Bank (Rs.250 crore).
The credit lines will help the company to meet the fund requirements, BG and LC requirements of the project for a period of 39 months.