Illustrative image – not actual.Brihanmumbai Electricity Supply and Transport (BEST) plans to improve its distribution network in Mumbai with an investment of Rs.672 crore during 2001-06.
According to a draft report, BEST plans use the funds
to improve reliability and security of power supply, reduce distribution losses
from the existing 10 per cent, maintain voltage profile, avoid power thefts,
automate the distribution system and computerise the system to make it
effective. BEST also plans to undertake low voltage cable laying work for
quicker restoration of power supply in case of fault. Accordingly, there are
plans to lay around 200 kms of cables each year.
BEST plans to install dry type transformers on a
large scale particularly in the distribution substations. Each year, for five
years, BEST plans to replace about 100 transformers. Plans are also afoot to
replace the existing 10 lakh conventional metres by electronic ones in a phased
manner.
BEST also plans to use the above mentioned funds to
construct a new distribution substation at 11 kv / 415 volt level, new
receiving substations at 110 kv / 33 kv / 22 kv level, laying of high voltage /
low voltage cables, communication network, electronic metres and test benches.