Illustrative image – not actual.The Bengaluru Suburban Transport Project (BSTP) has achieved 19.9 percent physical progress in three-and-a-half years up to July, according to implementing agency Rail Infrastructure Development Company (Karnataka), or K-RIDE.
The state government has also approved construction work at the Akkupete depot, while private land acquisition for its approach is underway. K-RIDE has confirmed that BSTP will adopt European Train Control System (ETCS) Level-2 across all corridors instead of the previously planned communications-based train control system. The signalling technology is also planned for India’s Mumbai-Ahmedabad high-speed rail project and is expected to improve safety through real-time train monitoring. The agency has invited tenders for around nine km of viaduct works under Corridor-2 and two major packages covering 22 km under Corridor-4.
A 1.2-km double-decker structure is also planned along Mohan Kumar Road, combining a road flyover and suburban rail corridor to optimise constrained urban space.