Bengaluru-Mysuru track doubling 1.7 km stretch commissionedIllustrative image – not actual.
The pending 1.7 km stretch of double track at Srirangapatna on the Bengaluru-Mysuru line has been commissioned.

With the commissioning of this stretch at Srirangapatna, the entire 138.3 km of double track between Bengaluru and Mysuru is completed and commissioned, excluding the electrification between Yeliyur-Mysuru stretch of 39 km. This stretch will also be completed soon.

The doubling of the railway track sanctioned in three phases will reduce the travelling time between Bengaluru and Mysuru.

While Stage-I, Bengaluru-Kengeri stretching over12.3 km was completed and commissioned in February 2007 at a cost of Rs 39.59 crore, Stage-II Kengeri-Ramanagaram stretching over 32.00 km was completed and commissioned in October 2008 at a cost of Rs 75.98 crore.

Stage-III envisaging doubling between Ramanagaram-Mysuru and electrification between Kengeri and Mysuru was taken up at an investment of Rs 875 crore on a cost sharing basis with the government of Karnataka.

Doubling of Ramanagaram-Mysuru stretching over 94 km was completed and commissioned in October 2015 except for a small stretch of 1.7 km at Srirangapatna which has now been commissioned.