The Ministry of Road Transport & Highways is likely to split the ten lane Bengaluru-Mysuru Expressway project into two packages so that the National Highways Authority of India (NHAI) can build it early.
The ministry is keen to start constructing the 118 km expressway from both, north and south end simultaneously.
NHAI has submitted the outlines of the expressway project to the ministry. It has almost completed land acquisition, while compensation to farmers is in progress.
The estimated land requirement for the project is 1,232 acre across seven taluks. The approximate cost for construction is Rs 3,695 crore, while land acquisition cost is Rs 2,400 crore.
NHAI will complete the bidding process before March 2017. The project is expected to be completed in around 30 months.