Bengaluru-Mysuru corridor Phase-I nears completionIllustrative image – not actual.

Nandi Infrastructure Corridor Enterprise’s project to develop 111 km of expressway connecting Bengaluru to Mysuru is nearing its Phase-I completion.


The company has made 56 km of 62 km and is waiting to acquire land for the same. In addition, it is awaiting approval for Phase-II and Phase-III work.


Nandi Infrastructure Corridor Enterprise is mulling a reverse merger of NICE with BF Utility, that owns 74 per cent stake.


Around 42-43 infrastructure projects were signed along with this project. From the 43 projects, only this one survived.


 