Illustrative image – not actual.Bechtel
has informed the Dabhol Power Company that it would pull out of the Enron
project if its dues were not settled by 31 May 2001.
Bechtel is the EPC contractor for the
2,184 MW Enron power project and is also a minority 10 per cent shareholder in
the project. The company has also informed that it would stop further construction
work at the site (Phase II) due to which the deadline of June 2001 would not be
met. Reportedly, around 15 per cent of civil work is yet to be completed.